The World Bank has prepared its first Subnational Doing Business report on Bulgaria, Hungary and Romania entitled Doing Business in the European Union 2017: Bulgaria, Hungary and Romania. The report is based on the surveys conducted last year by involving respondents from 6 cities in Bulgaria, 7 cities in Hungary and 9 cities in Romania, measuring 5 indicators: starting a business, dealing with construction permits, getting electricity, registering property and enforcing contracts.

In this subnational research in Hungary, Ebuild Hungary (the parent company of Ebuild Romania, EECFA’ s Romanian member) was responsible for choosing the respondents from the private sector in Hungary on 2 of the 5 Doing Business indicators: dealing with construction permits and getting electricity. EECFA Research, Buildecon, was responsible for coordinating the project on these 2 indicators in the private sector in Hungary. Buildecon also completes the World Bank’s National Doing Business survey on dealing with construction permits in Hungary every year; a survey regarded as a benchmark for investors.
Here we are going to take a look at the key findings on the dealing with construction permits indicator* in Bulgaria, Hungary and Romania, what regional variations are, how the processes could be improved according to the report, why Germany is so efficient in getting building permits and how Hungary is trying to follow suit.
Key findings on getting construction permits
It has been concluded that overall, it is in Hungary where it is the easiest to obtain a construction permit for a warehouse (18 procedures) compared to Bulgaria (19 procedures) and Romania (26 procedures). However, all countries are lagging behind the EU average of 13 procedures.
In terms of the length of the permitting process, it is in Bulgaria where the process is the quickest: on average 141 days, and it is in Romania where it takes the longest time: 256 days. In Hungary it is 164 days, though it is better than the relative EU average of 169 days. There are 2 EU member states, the Slovak Republic and Cyprus, where the process is very long – 286 days and 507 days, respectively.
As far as costs of the construction permit are concerned, it is in Hungary where it is the cheapest to get a permit (0.5% of the warehouse value) and it is in Romania where it is the most expensive (3.4%). Bulgaria is only slightly cheaper (3.2%). By comparison, the EU average is 2.0%.
All three countries have been found to make building regulations available online and clearly specify the requirements for a building permit. Also, it has been concluded that all three countries have strong building quality control mechanisms and strict qualification requirements for professionals responsible for permitting approvals.
On the other hand, in comparison with the EU, the report has found that in all three countries the construction permit procedure is much more burdensome than in most other EU member states. Continue reading Dealing with construction permits in Bulgaria, Hungary, Romania